Mungana gold open pit development project

Kagara Ltd is the proponent for the Mungana Gold Open Pit Development (MGOPD) Project. The proponent made application on 7 July 2009 under section 71 of the Environmental Protection Act 1994 for the preparation of a voluntary environmental impact statement (EIS). The application was approved on 10 July 2009.

The status of the process for the assessment of the MGOPD Project is as follows:

  1. Submission of draft TOR
  2. Public notification of draft TOR
  3. Final TOR issued—EIS in preparation
  4. Public notification of EIS
  5. Proponent responds to submissions
  6. EIS assessment report

The EIS assessment report was issued to Kagara Ltd on 7 September 2011 and the EIS process under Chapter 3, Part 1 of the EP Act has been completed.

Copies of documents that are available electronically can be obtained by accessing the links below:

For further information about the EIS process for the MGOPD Project please contact the EIS Co-ordinator.

Available from the library catalogue

The documents referred to on this page are available from the department’s online library catalogue.